SUP 125/24
11JUL24/11JUL25EST
NOTE: EST SUP will only be cancelled by NOTAM, SUP or AIP amendment.
ENAIRE
DIVISIÓN DE INFORMACIÓN AERONÁUTICA
c/ Campezo, 1. EDIFICIO 2
Kudos Innovation Campus Las Mercedes
28022 Madrid (ESPAÑA)
AIP-ESPAÑA
SUP 125/24
11-JUL-24
ENR
CANCEL: SUP 88/23
SUP 125/24
11JUL24/11JUL25EST
NOTE: EST SUP will only be cancelled by NOTAM, SUP or AIP amendment.
Until 11 July 2025 (estimated), five wind turbines and a meteorological tower will be under construction at Monte Tourado Wind Farm, in the municipality of Zas (A Coruña).
For its construction, the installation of a mobile crane will be necessary.
The projected height, elevation and location of each element are detailed in the table below:
ID | COORD | ELEV (M AMSL) | HGT (M) |
P21-0672 MT01 Windmill | 430422.77N 0085627.79W | 633 | 180 |
P21-0672 MT02 Windmill | 430317.92N 0085724.88W | 645 | 180 |
P21-0672 MT03 Windmill | 430318.01N 0085740.59W | 632 | 180 |
P21-0672 MT04 Windmill | 430415.40N 0085618.42W | 602 | 180 |
P21-0672 MT06 Windmill | 430229.81N 0085800.73W | 606 | 180 |
P21-0672 TM-MT2 MET tower | 430212.92N 0085751.37W | 488 | 105 |
P21-0672 Mobile crane | – | – | 145 |