ENAIRE
DIVISIÓN DE INFORMACIÓN AERONÁUTICA
c/ Campezo, 1. EDIFICIO 2
Kudos Innovation Campus Las Mercedes
28022 Madrid (ESPAÑA)
AIP-ESPAÑA
SUP 92/24
13-JUN-24
AD
CANCEL: SUP 114/23
SUP 92/24
13JUN24/13JUN25EST
NOTE: EST SUP will only be cancelled by NOTAM, SUP or AIP amendment.
Until 13 June 2025 (estimated), the installation of runway guard lights on the access roads to runway Y-1, Y-2 and Y-3 will be under way.
The works will be conducted in a single phase. The start and end dates of the phase of the works, as well as any operational incidents that may arise will be announced via the corresponding NOTAM.
No works will be performed when low visibility procedures are active.
During this phase, civil engineering works will be performed to enable the laying of cable, installation of runway guard lights and integration with the airport´s lighting system.
The works will be performed outside the airport’s operational hours.
No restrictions on operations are expected for the duration of the works.