SUP
35/26
19MAR26/19MAR27EST
NOTE: EST SUP will only be cancelled by NOTAM, SUP or AIP amendment.
ENAIRE
DIVISIÓN DE INFORMACIÓN AERONÁUTICA
c/ Campezo, 1. EDIFICIO 2
Kudos Innovation Campus Las Mercedes
28022 Madrid (ESPAÑA)
AIP-ESPAÑA
SUP
35/26
19-MAR-26
EFFECTIVE DATE WEF
ENR
CANCEL: SUP 78/25
SUP
35/26
19MAR26/19MAR27EST
NOTE: EST SUP will only be cancelled by NOTAM, SUP or AIP amendment.
Until 19 March 2027 (estimated), three wind turbines will be under construction in the municipality of Serón (Almería).
For its construction, the installation of a mobile crane will be necessary.
The projected height, elevation and location of each element are detailed in the table below:
ID | COORD | ELEV (M AMSL) | HGT (M) |
P20-0206_LB_01 | 372523.50N 0023516.35W | 1253 | 188 |
P20-0206_LB_02 | 372534.19N 0023453.59W | 1280 | 188 |
P20-0206_LB_03 | 372510.04N 0023527.45W | 1243 | 188 |
Mobile Crane | - | - | 125 |