SUP
38/26
19MAR26/19MAR27EST
NOTE: EST SUP will only be cancelled by NOTAM, SUP or AIP amendment.
ENAIRE
DIVISIÓN DE INFORMACIÓN AERONÁUTICA
c/ Campezo, 1. EDIFICIO 2
Kudos Innovation Campus Las Mercedes
28022 Madrid (ESPAÑA)
AIP-ESPAÑA
SUP
38/26
19-MAR-26
EFFECTIVE DATE WEF
ENR
CANCEL: SUP 86/25
SUP
38/26
19MAR26/19MAR27EST
NOTE: EST SUP will only be cancelled by NOTAM, SUP or AIP amendment.
Until 19 March 2027 (estimated), eight wind turbines will be under construction at Melguiza wind farm in the municipality of Caniles (Granada).
For their construction, the installation of one mobile crane will be necessary.
The projected height, elevation and location of each element are detailed in the table below:
ID | COORD | ELEV (M AMSL) | HGT (M) |
P20-0204_ME-01 | 372451.59N 0023844.45W | 1173 | 188 |
P20-0204_ME-02 | 372510.03N 0023847.58W | 1158 | 188 |
P20-0204_ME-03 | 372515.78N 0023827.86W | 1154 | 188 |
P20-0204_ME-04 | 372515.78N 0023804.39W | 1166 | 188 |
P20-0204_ME-08 | 372401.22N 0023830.13W | 1204 | 188 |
P20-0204_ME-09 | 372341.73N 0023824.94W | 1219 | 188 |
P20-0204_ME-10 | 372324.96N 0023824.85W | 1232 | 188 |
P20-0204_ME-11 | 372328.56N 0023847.45W | 1238 | 188 |
Mobile crane | - | - | 125 |