Until 08 August 2025 (estimated), nine wind turbines and a measuring tower will be under construction at La Paul Wind Farm, in the municipality of Valpalmas and Luna (Zaragoza).
For its construction, the installation of a mobile crane will be necessary.
The projected height, elevation and location of each element are detailed in the table below:
ID | COORD | ELEV (M AMSL) | HGT (M) |
P20-0233 PAU-01 Windmill | 420757.53N 0005001.72W | 666 | 200 |
P20-0233 PAU-02 Windmill | 420739.18N 0004952.93W | 643 | 200 |
P20-0233 PAU-03 Windmill | 420720.28N 0004932.89W | 637 | 200 |
P20-0233 PAU-04 Windmill | 420729.20N 0004945.59W | 628 | 200 |
P20-0233 PAU-05 Windmill | 420649.72N 0005012.69W | 638 | 200 |
P20-0233 PAU-06 Windmill | 420634.13N 0005030.20W | 639 | 200 |
P20-0233 PAU-07 Windmill | 420617.75N 0005007.73W | 623 | 200 |
P20-0233 PAU-08 Windmill | 420634.52N 0004946.88W | 606 | 200 |
P23-0223 PAU-09 Windmill | 420538.15N 0004935.95W | 595 | 200 |
P20-0233 PAU-TMP Tower | 420601.75N 0005009.97W | 527 | 135 |
P20-0233 Movil crane | - | - | 155 |