Until 31 October 2025 (estimated), three wind turbines will be under construction at the El Oliado Wind Farm, in the municipality of Sesma (Navarra).
For their construction, the installation of one mobile crane will be necessary.
The projected height, elevation and location of each element are detailed in the table below:
ID | COORD | ELEV (M AMSL) | HGT (M) |
P23-0155 OLI_1 Windmill | 422711.16N 0020620.66W | 644 | 200 |
P23-0155 OLI_2 Windmill | 422640.34N 0020650.48W | 640 | 200 |
P23-0155 OLI_3 Windmill | 422621.41N 0020707.86W | 607 | 200 |
P23-0155 Mobile crane | 138 |