Until 31 October 2025 (estimated), four wind turbines and a measuring tower will be under construction at Santa Cruz IV Wind Farm, in the municipality of Berbegal and Peralta de Alcofea (Huesca).
For its construction, the installation of a mobile crane will be necessary.
The projected height, elevation and location are detailed in the table below:
ID | COORD | ELEV (M AMSL) | HGT (M |
P22-0219 SC4-01 | 415622.07N 0000120.43E | 704 | 220 |
P22-0219 SC4-02 | 415602.92N 0000046.96E | 699 | 220 |
P22-0219 SC4-03 | 415340.05N 0000003.53E | 687 | 220 |
P22-0219 SC4-04 | 415422.71N 0000001.40W | 692 | 220 |
P22-0219 SC4-TP | 415626.09N 0000103.25E | 624 | 121 |
Mobile crane | - | - | 141 |