Until 23 Jaunary 2026 (estimated), four wind turbines will be under construction at Aldeavieja Repotenciación Wind Farm in the municipalities of Ojos-Albos and Santa María del Cubillo (Ávila).
For its construction, the installation of a mobile crane will be necessary.
The proyected height, elevation and location of each element are detailed in the table below:
ID | COORD | ELEV (M AMSL) | HGT (M) |
A-1 | 404302.26N 0042801.73W | 1748 | 194 |
A-2 | 404306.78N 0042824.07W | 1757 | 194 |
A-3 | 404314.57N 0042901.07W | 1783 | 194 |
A-4 | 404303.55N 0042918.60W | 1746 | 194 |
Mobile crane | - | - | 140 |