GIRONA AD (LEGE).- Works to replace ILS/DME RWY 19 “IGN”.

Until 13 June 2025 (estimated), updates related to the replacement of the ILS/DME RWY 19 “IGN” sistem will be underway.

The works will be conducted in three phases. The works described for each phase and zone will not necessarily be executed simultaneously, rather they will be scheduled based on the operations affected.

The start and end dates of each phase , as well as any operational incidents that may arise, will be announced via the  corresponding NOTAM.

All work areas will be duly marked and lit.

PHASE 1: Preliminary stockpiling and stakeout

No operational impact on ILS.

PHASE 2: Disconnection of GP/DME RWY 19

The actions will be performed with GP/DME RWY 19 out of service.

These tasks will require workers and machinery to be present in the zone and in the critical area of GP/DME RWY 19.

The following instrument approach procedures will not be usable (U/S):

Other procedures will be operational.

PHASE 3: Disconnection of ILS/DME RWY 19

The actions shall be performed with the I ILS/DME RWY 19 (LOC and GP/DME RWY 19) system completely out of service.

These tasks will require workers and machinery to be present in the zone and in the critical area of GP/DME RWY 19 and LOC RWY 19.

The following instrument approach procedures will not be usable (U/S):

Other procedures will be operational.

SUP 75/24