LANZAROTE/César Manrique Lanzarote AD (GCRR).- Works to replace ILS/DME RWY 03 “IRR”.

Until 20 March 2026 estimated, works to replace the ILS/DME RWY 03 “IRR” will be underway.

The works will be carried out in two phases. The works described for each phase and zone will not necessarily be executed simultaneously rather they will be scheduled based on the operations affected.

The start and end dates of each phase, as well as any operational incidents that may arise, will be announced via the corresponding NOTAM.

All work areas will be duly marked and lit.

 

Phase 1: Preliminary stockpiling and stakeout

The works to be performed in this stage will mainly consist of:

Stockpiling material near the LOC shed and in the cistern zone located next to the service road 150 metres to the south of the LOC.

Stakeout and topographical works prior to disconnection.

No operational impact on ILS.

 

Phase 2: Disconnection of ILS/DME RWY 03

The actions shall be performed with the ILS/DME RWY 03 (LOC and GP/DME RWY 03) system completely out of service.

These tasks will require workers and machinery to be present in the zone and in the critical area of GP/DME RWY 03 and LOC RWY 03.

The following instrument approach procedures will not be usable (U/S):

  • AD 2 GCRR IAC/1 - ILS Z RWY 03

  • AD 2 GCRR IAC/4 - LOC Z RWY 03

  • AD 2 GCRR IAC/11 - HI-ILS RWY 03

  • AD 2 GCRR IAC/12 - HI-LOC RWY 03

Other procedures will be operational..