Until 16 April 2027 (estimated), five wind turbines and a measurement tower will be under construction at Joluga wind farm in the municipality of Eslava (Navarra).
For its construction, the installation of three mobile cranes will be necessary.
The projected height, elevation and location of each element are detailed in the table below:
ID | COORD | ELEV (M AMSL) | HGT (M) |
P25-0084-JOL-01 Wind turbine | 423453.78N 0012630.57W | 1033 | 180 |
P25-0084-JOL-02 Wind turbine | 423456.18N 0012652.27W | 1023 | 180 |
P25-0084-JOL-03 Wind turbine | 423501.32N 0012710.39W | 1032 | 180 |
P25-0084-JOL-04 Wind turbine | 423510.13N 0012736.28W | 1034 | 180 |
P25-0084-JOL-05 Wind turbine | 423518.55N 0012755.07W | 1009 | 180 |
P25-0084-JOL-TP Measurement tower | 423505.58N 0012723.49W | 942 | 105 |
P25-0084-Mobile crane 1 | - | - | 150 |
P25-0084-Mobile crane 2 and 3 | - | - | 120 |