PALMA DE MALLORCA AD (LEPA/LESJ).- Works to remodel of Module A and the Terminal (West Apron).

Until 01 October 2027 (estimated), works for the final reconfiguration of the north-west apron of Palma de Mallorca Airport shall be underway.

The work will take place in 11 phases, the areas affected in each are those specified in the present document.

The phases might not necessarily be executed in the order defined, and several phases or subphases might be activated simultaneously.

The start and end dates of each phase, as well as any operational incident, will be by the corresponding NOTAM.

All phases of the works shall be duly marked and lit. Caution is recommended due to the presence of personnel and machinery.

Work Scheduling and Coordination

The works will be performed at daytime or at night time. If any action affects any airport service or operations, the day and time slot will be coordinated in order to execute the works.

PHASE 1. CLOSURE OF PRKG 02

The operational restriction during this phase is the closure of PRKG 02.

PHASE 2. CLOSURE OF PRKG 03

The operational restriction during this phase is the closure of PRKG 03.

PHASE 3. CLOSURE OF PRKG 04

The operational restriction during this phase is the closure of PRKG 04.

PHASE 4. CLOSURE OF PRKG 05

The operational restriction during this phase is the closure of PRKG 05.

PHASE 5. CLOSURE OF PRKG 06

The operational restriction during this phase is the closure of PRKG 06.

PHASE 6. CLOSURE OF PRKG 06A

The operational restriction during this phase is the closure of PRKG 06A.

PHASE 7. CLOSURE OF PRKG 06B

The operational restriction during this phase is the closure of PRKG 06B.

PHASE 8. CLOSURE OF PRKG 08

The operational restriction during this phase is the closure of PRKG 08.

PHASE 9. NEW CONFIGURATION OF PRKG 05

The new configuration of PRKG 05 will be as follows:

 

PRKG

RAMP

COORD

EXIT

MAX ACFT

APROAR NOSE TO

REMARKS

      05    

R3

393255.85N 0024328.00E

R

A321

E

-

PHASE 10. CLOSURE OF TAXIWAY LD

The operational restriction during this phase will be the closure of Taxiway LD, and consequently, the closure of PRKG 100, 100B, 101, 102, 103, 103B.

PHASE 11. NEW CONFIGURATION OF PRKG 06B

The new configuration of PRKG 06B will be as follows:

PRKG

RAMP

COORD

EXIT

MAX ACFT

APROAR NOSE TO

REMARKS

    06B 

R3

393258.00N 0024332.76E

R

B3XM

E

INCOMP. 06

400 Hz - A/C (1) (2)

(1) Visual docking guidance system.

(2) Parking manoeuvre in stands in contact with the terminal building shall be accomplished only where the docking guidance systems is operative or a marshaller aid is available.