SUP
19/26
AIRAC 05-FEB-26
EFFECTIVE DATE WEF 19-MAR-26
AD
CANCEL:
SUP
19/26
19MAR26/19MAR27EST
NOTE: EST SUP will only be cancelled by NOTAM, SUP or AIP amendment.
Until 19 March 2027 (estimated), repair and improvement works will be carried out on the rigid pavement of the South apron.
The work areas shall be duly marked and lit. Caution is recommended due to the presence of personnel and machinery.
No works will be performed when low visibility procedures are active.
The start and end dates, as well as any operational incidents that may arise, will be announced via the corresponding NOTAM.
The phases may not necessarily be completed in the given order. The stages may be jointly worked on.
Schedule:
The works shall be carried out during the airport’s operational and non-operational hours.
Operational restrictions:
PRKG G13, G12A, G14A and HG13 U/S.
Schedule:
The works shall be carried out during the airport’s operational and non-operational hours.
Operational restrictions:
PRKG G12, G12A and HG12 U/S.
Schedule:
The works shall be carried out during the airport’s operational and non-operational hours.
Operational restrictions:
PRKG G11 and G12A U/S.
Schedule:
The works shall be carried out during the airport’s operational and non-operational hours.
Operational restrictions:
PRKG G9, G10 and G10A U/S.
Schedule:
The works shall be carried out during the airport’s non-operational hours.
Operational restrictions:
Sin restricciones operativas.
Schedule:
The works shall be carried out during the airport’s operational and non-operational hours.
Operational restrictions:
PRKG G4 and G5 U/S.
Schedule:
The works shall be carried out during the airport’s non-operational hours.
Operational restrictions:
No operational restrictions.
Schedule:
The works shall be carried out during the airport’s operational and non-operational hours.
Operational restrictions:
PRKG G6, G7 and G8 U/S.
Schedule:
The works shall be carried out during the airport’s non-operational hours.
Operational restrictions:
No operational restrictions.