CANCEL: SUP 58/24
SUP
46/25
20MAR25/20MAR26EST
NOTE: EST SUP will only be cancelled by NOTAM, SUP or AIP amendment.
Until 20 March 2026 (estimated), twelve winds turbine will be under construction and two measurement towers at Treboada Wind Farm, in the municipalities of San Xoán de Río, Castro Caldelas and Chandrexa de Queixa (Ourense).
For its construction the installation of a mobile crane will be necessary.
The projected height, elevation and location of each element, which will not be neither marked nor lit, are detailed in the table below.
ID | COORD | ELEV (M AMSL) | HGT (M) |
P23-0118 T1 Windmill | 422416.88N 0072050.01W | 1120 | 180 |
P23-0118 T2 Windmill | 422403.55N 0072103.04W | 1130 | 180 |
P23-0118 T3 Windmill | 422343.52N 0072121.76W | 1130 | 180 |
P23-0118 T4 Windmill | 422332.05N 0072135.53W | 1120 | 180 |
P23-0118 T5 Windmill | 422321.51N 0072200.26W | 1110 | 180 |
P23-0118 T6 Windmill | 422048.61N 0072045.63W | 1212 | 180 |
P23-0118 T7 Windmill | 422041.71N 0072059.67W | 1220 | 180 |
P23-0118 T8 Windmill | 422032.79N 0072110.78W | 1250 | 180 |
P23-0118 T9 Windmill | 422023.99N 0072123.21W | 1210 | 180 |
P23-0118 T10 Windmill | 422212.25N 0071929.55W | 1166 | 180 |
P23-0118 T11 Windmill | 422200.20N 0071932.54W | 1140 | 180 |
P23-0118 T12 Windmill | 422143.41N 0071919.04W | 1130 | 180 |
P23-0118 TM-T1 Tower | 422355.07N 0072106.55W | 1063 | 108 |
P23-0118 TM-T2 Tower | 422050.18N 0072030.73W | 1128 | 108 |
P23-0118 Mobile crane | - | - | 115 |