SUP 97/25
15MAY25/15MAY26EST
NOTE: EST SUP will only be cancelled by NOTAM, SUP or AIP amendment.
ENAIRE
DIVISIÓN DE INFORMACIÓN AERONÁUTICA
c/ Campezo, 1. EDIFICIO 2
Kudos Innovation Campus Las Mercedes
28022 Madrid (ESPAÑA)
AIP-ESPAÑA
SUP
97/25
15-MAY-25
ENR
CANCEL: SUP 05/25
SUP 97/25
15MAY25/15MAY26EST
NOTE: EST SUP will only be cancelled by NOTAM, SUP or AIP amendment.
Until 15 May 2026 (estimated), seven wind turbines will be under construction at A Ruña II Wind Farm in the municipality of Mazaricos (A Coruña).
For its construction, the installation of two mobile crane will be necessary that will move to the location of each wind turbine to proceed with its lifting.
The projected height, elevation and location of each element are detailed in the table below:
ID | COORD | ELEV (M AMSL) | HGT (M) |
P22-0256 A01 Windmill | 425705.01N 0090359.95W | 522 | 150 |
P22-0256 A02 Windmill | 425636.32N 0090355.24W | 598 | 150 |
P22-0256 A03 Windmill | 425603.41N 0090306.98W | 681 | 150 |
P22-0256 A04 Windmill | 425507.11N 0090337.63W | 735 | 150 |
P22-0256 A05 Windmill | 425509.35N 0090430.13W | 601 | 150 |
P22-0256 A06 Windmill | 425530.70N 0090456.31W | 551 | 150 |
P22-0256 A07 Windmill | 425537.24N 0090505.01W | 532 | 150 |
Mobile crane 1 | - | - | 125 |
Mobile crane 2 | - | - | 125 |