SUP
099/26
14MAY26/14MAY27EST
NOTE: EST SUP will only be cancelled by NOTAM, SUP or AIP amendment.
ENAIRE
DIVISIÓN DE INFORMACIÓN AERONÁUTICA
c/ Campezo, 1. EDIFICIO 2
Kudos Innovation Campus Las Mercedes
28022 Madrid (ESPAÑA)
AIP-ESPAÑA
SUP
099/26
14-MAY-26
EFFECTIVE DATE WEF
ENR
CANCEL: SUP 081/26
SUP
099/26
14MAY26/14MAY27EST
NOTE: EST SUP will only be cancelled by NOTAM, SUP or AIP amendment.
Until 14 May 2027 (estimated), three wind turbines will be under construction at Carrugueiro Wind Farm, in the municipality of Boal (Asturias).
The projected height, elevation and location of each element are detailed in the table below:
ID | COORD | ELEV (M AMSL) | HGT (M) |
P21-0713-AE01 | 432448.94N 0065128.12W | 1066 | 150 |
P21-0713-AE02 | 432441.89N 0065118.98W | 1094 | 150 |
P21-0713-AE03 | 432430.83N 0065121.91W | 1063 | 150 |