FIR BARCELONA.- Concejo III Wind Farm under construction.

Until 17 April 2026 (estimated), seven wind turbines and a meteorological tower will be under construction at the Concejo III Wind Farm, in the municipality of Cantavieja (Teruel).

For their construction, the installation of one mobile crane will be necessary.

The projected height, elevation and location of each element are detailed in the table below:

ID

COORD

ELEV (M AMSL)

HGT (M)

P23-0042-CJ3-01

402809.36N 0002320.71W

1855

200

P23-0042-CJ3-02

402830.41N 0002312.29W

1842

200

P23-0042-CJ3-03

402850.53N 0002301.49W

1834

200

P23-0042-CJ3-04

402904.83N 0002247.26W

1822

200

P23-0042-CJ3-06

402917.34N 0002333.83W

1828

200

P23-0042-CJ3-07

402914.39N 0002358.32W

1842

200

P23-0042-CJ3-08

402859.79N 0002412.56W

1856

200

P23-0042-CJ3-TMA Meteorological tower

402936.24N 0002337.90W

1755

120

P23-0042-CJ3-01 Mobile crane

402809.36N 0002320.71W

-

140