Until 17 April 2026 (estimated), four wind turbines will be under construction at La Estrella Wind Farm in the municipality of Mosqueruela (Teruel).
The projected height, elevation and location of each element are detailed in the table below:
ID | COORD | ELEV (M AMSL) | HGT (M) |
P23-0053-LE4-04 | 402448.64N 0002054.14W | 1744 | 200 |
P23-0053-LE4-05 | 402409.93N 0001935.70W | 1743 | 200 |
P23-0053-LE4-06 | 402355.94N 0001946.35W | 1727 | 200 |
P23-0053-LE4-07 | 402347.60N 0002006.82W | 1680 | 200 |