Until 14 May 2027 (estimated), four wind turbines and one measurement tower will be under construction at Montañés Wind Farm, in the municipality of Zaragoza (Zaragoza).
For its construction, the installation of a mobile crane will be necessary.
The projected height, elevation and location of each element are detailed in the table below:
ID | COORD | ELEV (M AMSL) | HTG (M) |
P17-0127-AE02 Wind turbine | 413435,08N 0005327,98W | 501 | 150 |
P17-0127-AE03 Wind turbine | 413419,17N 0005302,46W | 512 | 180 |
P17-0127-AE04 Wind turbine | 413431,71N 0005247,84W | 527 | 180 |
P17-0127-AE06 Wind turbine | 413401,98N 0005223,47W | 508 | 180 |
P17-0127-TM Measurement tower | 413432,21N 0005341,41W | 478 | 99 |
P17-0127 Mobile crane | - | - | 125 |