Until 14 May 2027 (estimated), three wind turbines will be under construction at Carrugueiro Wind Farm, in the municipality of Boal (Asturias).
The projected height, elevation and location of each element are detailed in the table below:
ID | COORD | ELEV (M AMSL) | HGT (M) |
P21-0713-AE01 | 434135.93N 0068578.10W | 916 | 150 |
P21-0713-AE02 | 434116.36N 0068552.72W | 944 | 150 |
P21-0713-AE03 | 434085.63N 0068560.85W | 912 | 150 |